Murtala Muhammed Airport — Runway Resurfacing
Resurfacing of the tarmac runway for the Federal Airports Authority of Nigeria (FAAN) at Murtala Muhammed International Airport — Nigeria's busiest aviation hub
₦285 Million
Murtala Muhammed International Airport, Lagos
6 months
2016
Project Overview
The Murtala Muhammed International Airport runway resurfacing project stands as one of Envostructs' most operationally critical infrastructure achievements. Commissioned by the Federal Airports Authority of Nigeria (FAAN) — the federal agency managing all commercial airports in Nigeria — the project involved resurfacing of the main tarmac runway at Nigeria's busiest airport, which handles millions of domestic and international passengers annually across its 3.9 km runways. Airport runway works demand extreme precision: all operations must be completed within defined FAAN maintenance windows to minimize flight disruptions, the pavement must meet ICAO and FAA international standards for friction, smoothness, and load capacity, and all works must pass independent airside safety validation before the runway returns to service.
Project Gallery
Challenges & Solutions
Challenges
- All works within tightly scheduled FAAN maintenance windows — runway closures limited to specific overnight periods to minimize flight disruptions
- Pavement design to ICAO Category I standards — specific bituminous mix designs, surface texture depths, and aircraft load capacity ratings
- Full FAAN airside safety accreditation — coordinating with Air Traffic Control, ground handling, and airport operations throughout
- Independent runway surface friction testing required to meet international aviation acceptability criteria before return to service
Our Solutions
- Night-works programme developed with FAAN — all machinery prepositioned and tested before each curfew window opened
- Bituminous pavement mix designed and laboratory-tested to confirm ICAO friction and smoothness compliance
- Full airside safety protocol: fluorescent PPE, airside briefings, marshalling, and Foreign Object Debris (FOD) control at all times
- Independent friction testing by FAAN-approved agency before return-to-service certification issued
Key Features
Project Information
Client
Federal Airports Authority of Nigeria (FAAN)
Project Manager
Engr. A.D. Onitilo
Duration
6 months
Completion Year
2016
Status
CompletedTechnical Specifications
Project Timeline
Mix Design, Design & FAAN Approvals
6 weeks
CompletedMilling & Surface Preparation
4 weeks
CompletedLevelling Course & Surface Course
8 weeks
CompletedMarkings, Testing & Return to Service
6 weeks