Mile 12 – Ikorodu Road (World Bank)
Independent quality control and safety supervision on the World Bank-funded rehabilitation of the critical Mile 12 to Ikorodu arterial corridor in Lagos State
₦215 Million
Mile 12 to Ikorodu, Lagos State
18 months
2017
Project Overview
The Mile 12–Ikorodu Road is one of Lagos State's most heavily trafficked arterial corridors, connecting the iconic Mile 12 International Market — one of West Africa's largest commodity markets for food and agricultural produce — through the northern Lagos mainland to Ikorodu town. The road serves millions of daily commuters and is a critical supply route for produce traders. Envostructs was engaged to provide independent quality control and safety supervision on the World Bank-funded rehabilitation works, ensuring the contractor's outputs met international standards before drawdown of World Bank financing. World Bank-funded projects carry stringent procurement, QA, and Environmental and Social Safeguards requirements, all of which Envostructs managed through its resident supervision team.
Project Gallery
Challenges & Solutions
Challenges
- Supervising works on one of Lagos' busiest roads while managing extremely high traffic volumes and pedestrian exposure
- World Bank quality and procurement standards — all materials, testing, and reporting required to meet the Bank's fiduciary requirements
- Environmental and social safeguards compliance including dust suppression, noise management, and protection of roadside traders
- Multiple simultaneous contractor work fronts along the extended urban corridor
Our Solutions
- Resident supervision team with lane-by-lane traffic management plan — safe construction zones maintained alongside live traffic
- World Bank-compliant quality assurance system — all materials tested at accredited Lagos laboratories before site use
- Environmental and Social Management Plan supervision — weekly compliance checks and reporting to the World Bank coordination unit
- Multiple resident engineer checkpoints along the corridor, with daily reports to the Ministry of Works PMU
Key Features
Project Information
Client
Lagos State Ministry of Works — World Bank LFZRP
Project Manager
Engr. A.D. Onitilo
Duration
18 months
Completion Year
2017
Status
CompletedTechnical Specifications
Project Timeline
Baseline Survey & Supervision Mobilisation
2 months
CompletedEarthworks & Drainage Supervision
6 months
CompletedPavement Works Quality Control
7 months
CompletedCompletion Inspection & World Bank Reporting
3 months